Project Timeline



The project timeline reflects the NEPA process and the conceptual engineering phase. The environmental process and conceptual engineering for the Assembly Street Railroad Separation Project was initiated in March 2018. An agency scoping meeting will be held in May 2018. The first public information meeting will be held in June 2018. Alternatives development is anticipated to occur from May 2018 to May 2019, while conceptual engineering will occur from June 2018 to December 2018. The second public information meeting is anticipated to occur in Fall 2018, while the third public information meeting is anticipated to occur in early 2019. The draft environmental document is anticipated in April 2019, while the final environmental document is expected in September 2019. The Public Hearing is anticipated to occur in late 2019, with a final environmental decision expected in early 2020. This schedule is subject to change at any time.